At 19:30 on April 21st, with the completion of the last cubic meter of concrete pouring, it marked the successful completion of the gasification device constructed by No.6 ...
Under the support of the company leadership, company hospital as the industrial community health service center greets new equipment - new ten seats Iveco community health s...
At 3 PM of May 22nd, the company audit department held a seminar aboutanti-corruption education, Mr. Wei Daocheng, the deputy party secretary, secretary of discipline committ...
On April 25th, the Party committee of the company holds the party building work and the "two learning and one doing" learning exchange meeting. Each branch secretary and o...
On May 26th, Hebei Ai Kerui Co. 60,000 t/a acrylic project of Jilin Chemical Fiber Group undertaken by ELECO held a grand completion ceremony, marking the company successfu...
At 10:15 on May 4th, the Xinjiang Zhongtai chemical new material factory project has achieved a 35 thousand volt substation once energized successfully, which means that the...
To thoroughly study and implementthe spirit of the sixth plenary session of the 18th CPC central committee, according to the requirements of the company, combined with the ...
On May 11, hoisting the tube bundle of air cooler frame in Xinfeng company 1,000,000 tons per year gas separation tower for gas separating de-alkane tower rebuild project ...
On July 9th, the 4 heating furnace air preheaters of Urumqi petrochemical refinery aromatic coking furnace air preheater hazard treatment project contracted to build by the ...
Recently, the E&I item of Malaysia TR Project Departmentheld construction promotion meeting on site conference room. It is summed up the site construction of E&I some tim...