Henan Longyu Cooling Tower on Position
administrator
2017-08-28 10:54:00
Cooling tower shell is located at the 2.5 meters south of the 1-2 axis of the gasification device with 0.1 meters elevation, which weighs 126 tons, 3.6 meters in diameter and 22 meters high. The hoisting space of the cooling tower is limited and can not be hoisted normally. After the detailed site measurement, the 400t crawler crane is selected for hoisting. In the process of expert demonstration of hoisting scheme,it has received the guidance of a number of experts to provides a strong technical support for safe and smooth hoisting.
The equipment is successfully hoisted in place from the approach to finished unload within one day to achieve safe and high-efficiency. The cooling tower successfully hoisting will make full efforts to ensure the completion of the machinery in October 10th and the implementation of the targets for operation in October 30th!(Correspondent and Photography Reporter:Song Sifeng)