At 6
th of June am, steel structure roof of the200t urea frame has been a successful lifted which belong to the Qi Taihe Project built by Shanxi Branch Company.
The hoisting work mainly used 750 ton crane andequalizing beam. The large tons of steel structure and limited space make it hard to the hoisting work. The technical directors made a careful lifting scheme and plan to ensure a successful hoisting, also with some skilled and experienced lifting operators. At 10 am, along with the hoisting command issued,field staff worked closely, the steel structure frame to be slowly lifted, finally safe and smooth on the basis. It laid a solid foundation for the follow-up construction.
(Correspondent Liu Siyuan, Jiao Derui reproted)